Motorists should expect the reconstructed southbound weigh station on I-75 at mile marker 160 to reopen for service on Tuesday, April 11. Crews have completed work on the reconstruction of the facility.
Also, on Tuesday, April 11, crews will begin demolition on the northbound I-75 weigh station. Crews will begin to demolish and rebuild the northbound weigh station on the east side of the roadway. Motorists should expect the I-75 northbound weigh station facility to be closed to the public.
Motorists should not expect lane closures on I-75. Estimated completion is end of summer 2017. The contractor is R.M. Williams Construction, Inc.