Wekiva Parkway Section 7B Begins Construction

Posted on July 16, 2019

As Part of Building the Wekiva Parkway

Construction has begun to widen State Road (S.R) 46 to six lanes from Orange Boulevard to Oregon Street-Wayside Drive as part of building the Wekiva Parkway. [Read more…] about Wekiva Parkway Section 7B Begins Construction

Filed Under: Government Tagged With: FDOT, florida department of transportation, Wekiva Parkway

Public Information Open House for Wekiva Parkway Section 7B

Posted on July 1, 2019

The Florida Department of Transportation (FDOT) is holding a pre-construction public information open house about the Wekiva Parkway Section 7B project in Seminole County to review the anticipated non-tolled road improvements. [Read more…] about Public Information Open House for Wekiva Parkway Section 7B

Filed Under: Government Tagged With: FDOT, florida department of transportation, Wekiva Parkway

Contractor Selected to Build Final Wekiva Parkway Section

Posted on May 31, 2019

Marking a major project milestone, the Florida Department of Transportation (FDOT) selected Masci General Contractors, Inc. to build Section 7B, the final section of the $1.6 billion Wekiva Parkway. [Read more…] about Contractor Selected to Build Final Wekiva Parkway Section

Filed Under: Government Tagged With: FDOT, Wekiva Parkway

SEMA Construction Selected to Complete Wekiva Parkway Section 7A

Posted on May 30, 2019

The surety bond company has selected a new contractor to finish construction of Section 7A of the Wekiva Parkway (State Road (S.R.) 429) in Seminole County. [Read more…] about SEMA Construction Selected to Complete Wekiva Parkway Section 7A

Filed Under: Government Tagged With: florida department of transportation, Wekiva Parkway

State Road 46 Barrier Wall Work Requires Lane Closure

Posted on April 11, 2019

As Part of Building the Wekiva Parkway

Crews are scheduled at night Monday, Apr. 15, through Wednesday, Apr. 17, to close westbound State Road (S.R.) 46 from Old McDonald Road to State Road (S.R.) 429. [Read more…] about State Road 46 Barrier Wall Work Requires Lane Closure

Filed Under: Government Tagged With: florida department of transportation, Wekiva Parkway

Informational Open House for Wekiva Parkway Section 8

Posted on November 8, 2018

FDOT Logo

The Florida Department of Transportation (FDOT) is holding a pre-construction informational open house about the Wekiva Parkway Section 8 Project in Seminole County. [Read more…] about Informational Open House for Wekiva Parkway Section 8

Filed Under: Government Tagged With: FDOT, florida department of transportation, Wekiva Parkway

Wekiva Parkway Section 7A Construction Ramps Up

Posted on April 23, 2018


Construction activities will increase on State Road (S.R.) 46, west of Sanford during the week of April 22, and motorists should be alert for large construction equipment and vehicles entering and exiting multiple areas of the work zone. The work is for the expansion of the Wekiva Parkway project.

Activities include installing drainage pipe under the Florida Gas Transmission line along the north side of S.R. 46 west of Longwood-Markham Road. Other significant utility work will include Florida Power & Light installing lines underground on both sides of S.R. 46. Work also includes driving sheet pile for retaining walls along the north side of S.R. 46 across from Lake Markham Road.

The contractor has safely relocated gopher tortoises – a protected, keystone species – to a state licensed recipient site. Work is continuing and, so far, 98 of the reptiles have been excavated from 148 burrows. Once the tortoises are safely excavated, crews are clearing and grubbing these areas.

Drivers should exercise extra caution within the construction zone. FDOT asks that you pay attention to speed limit signs and all construction signs and safety devices.

Construction is scheduled to finish in 2022. Please note schedules may change due to weather or other circumstances. Updates are available on wekivaparkway.com, cflroads.com and by following the project on Facebook and Twitter (@WekivaPKWYinfo).

Media inquiries should contact Steve Olson, FDOT Communications Manager, at [email protected], or by telephone at 386-943-5479.

Filed Under: Featured Tagged With: construction, FDOT, Section 7A, Wekiva Parkway

Public Information Meeting for Wekiva Parkway Section 7A

Posted on February 15, 2018

The Florida Department of Transportation (FDOT) is holding a pre-construction public information meeting about the Wekiva Parkway Section 7A project in Seminole County. The public meeting is being held to review the construction plans and schedule.

This project is funded for construction of 3.5 miles of limited access toll road along the existing State Road (S.R.) 46 corridor from a half mile east of Wekiva Park Drive to Orange Boulevard. The project also includes parallel, non-tolled, one-lane frontage roads for local travel. Roundabouts are planned as safety enhancements at the intersections under the parkway. Lighting is planned under the bridges and on frontage road approaches to the roundabouts. Work is scheduled to begin in February or March of 2018.

The meeting is scheduled for Thursday, Feb. 22 from 5:30-7:30 p.m. at Lakeside Fellowship United Methodist Church’s new location: 121 N. Henderson Lane in Sanford. The meeting is an informal open house where plans are available for review and project staff is available to address questions.

Persons who require accommodations under the Americans with Disabilities Act or persons who require translation services, free of charge, should contact Ms. Mary Brooks, Quest Corporation of America, by writing to her at 2431 Aloma Avenue, Suite 231, Winter Park, FL 32792, by calling 407-694-5505 or contacting her via email at [email protected]. If you are hearing or speech impaired, please contact us by using the Florida Relay Service, 800-955-8771 (TDD) or 800-955-8770 (Voice).

Public participation is sought without regard to race, color, national origin, age, sex, religion, disability or family status.  Persons wishing to express their concerns relative to FDOT compliance with Title VI may do so by contacting Jennifer Smith, FDOT District Five Title VI Coordinator by email at [email protected].

For media inquiries, please contact Steve Olson, FDOT communications manager, at [email protected], or 386-943-5479. Maps and other project information can be found at www.wekivaparkway.com. Follow the project on Facebook and Twitter for real-time updates.

Filed Under: Featured Tagged With: FDOT, Public Information Meeting, Wekiva Parkway

Traffic Diversion Coming in February at U.S. 441 and S.R. 46 as Part of the Wekiva Parkway Project

Posted on January 24, 2018


Motorists seeing construction work at U.S. 441 and State Road (S.R.) 46 in the Mount Dora area, should be prepared for an upcoming temporary traffic pattern change. In February, all U.S. 441 traffic, and some traffic on S.R. 46 at night, will be diverted along the S.R. 46 southbound on- and off-ramps as part of the Wekiva Parkway/S.R. 429 project. This temporary change also includes a traffic signal at S.R. 46 (see exhibit attached.)
The traffic diversion will allow crews to rebuild this portion of U.S. 441 (shown as the red hashed area in the graphic), which includes removing the overpass bridges. During the nighttime removal of the U.S. 441 bridges, S.R. 46 traffic also will shift onto the nearby temporary pavement. Construction will start with removing the U.S. 441 bridges and building the east side, or future northbound lanes, and the new flyover bridge. Once the east side/future northbound lanes are complete, traffic will switch onto those new lanes while work begins on the west side, or the new southbound lanes.
Post-construction (see attached), the U.S. 441 and S.R. 46 interchange will be an at-grade/ground level, signalized intersection with a flyover ramp that will provide continuous traffic flow for southbound traffic heading east on S.R. 46 toward the parkway.
Once the new outside northbound and southbound lanes of U.S. 441 have been built, traffic will be split to allow building the median and turn lanes.
This work is part of the Wekiva Parkway Sections 3A and 3B construction that began on October 30, 2017, and is scheduled to finish in spring of 2020.
More Project Information
The $1.6 billion Wekiva Parkway will complete the beltway around Central Florida while helping to protect the natural resources surrounding the Wekiva River. The Florida Department of Transportation and the Central Florida Expressway Authority have been working together to build the 25-mile toll road, which provides travel alternatives, enhances safety and relieves congestion on local roads.
Environmentalists refer to the Wekiva Parkway as a good example of transportation planning through environmentally sensitive areas. Authorized by the 2004 Wekiva Parkway & Protection Act, parkway development has included conserving more than 3,400 acres of land. The parkway will include four expansive wildlife bridges, and will be largely elevated to reduce accidents between vehicles and wildlife.
Inclement weather or other unforeseen circumstances could delay or prolong work. Motorists are urged to use caution in the construction area for their safety and that of the work crews.
Maps and other project information can be found at wekivaparkway.com.

Filed Under: Featured Tagged With: FDOT, Wekiva Parkway

Public Information Meeting for Wekiva Parkway Section 7B

Posted on May 9, 2017


The Florida Department of Transportation (FDOT) is holding a public information meeting about the Wekiva Parkway Section 7B Design Project in Seminole County. The public meeting is being held to review the preliminary design for these non-tolled road improvements.
This project is funded for construction. The project limits are State Road (S.R.) 46 from Orange Boulevard to Wayside Drive-Oregon Street. This design project involves 1.31 miles of improvements, including designing roadway widening, safety medians, sidewalk, bike lanes, traffic signal upgrades, drainage, sign and pavement markings, utilities and other roadway features.
The meeting is scheduled for Tuesday, May 16, 2017, from 5:30 p.m. to 7:30 p.m. at Lakeside Fellowship United Methodist Church located at 305 S. Orange Boulevard in Sanford. The meeting is an informal open house where plans are available for review and project staff is available to address questions.
Persons who require accommodations under the Americans with Disabilities Act or persons who require translation services, free of charge, should contact: Ms. Mary Brooks, Quest Corporation of America, by writing to her at 2431 Aloma Avenue, Suite 231, Winter Park, FL 32792, by calling 407-694-5505 or contacting her via email at [email protected] at least seven (7) days prior to the meeting. If you are hearing or speech impaired, please contact us by using the Florida Relay Service, 800-955-8771 (TDD) or 800-955-8770 (Voice).
Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status.  Persons wishing to express their concerns relative to FDOT compliance with Title VI may do so by contacting Jennifer Smith, FDOT District Five Title VI Coordinator by phone at 386-943-5367, or via email at [email protected].
If you have any questions, please contact Steve Olson, FDOT Public Information Manager at [email protected], or by telephone at 386-943-5479. You may also contact Public Information Officer Mary Brooks at [email protected], or by telephone at 407-694-5505. For more information visit the project website at www.wekivaparkway.com, and follow the project on Facebook and Twitter.

Filed Under: Featured Tagged With: FDOT, Public Information Meeting, Wekiva Parkway

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Go to Next Page »

Primary Sidebar

    Submit News    

Florida Democratic Party Launches “Defend Our Dems” Program

Tallahassee, FL — Today, the Florida Democratic Party is proud to launch the “Defend Our Dems” program, an … [Read More...] about Florida Democratic Party Launches “Defend Our Dems” Program

House Democratic Leader Fentrice Driskell, Representatives Kelly Skidmore and Allison Tant Request FLDOE to Release Critical Data

TALLAHASSEE, Fla. – Earlier today, House Democratic Leader Fentrice Driskell (D–Tampa), Representative Kelly … [Read More...] about House Democratic Leader Fentrice Driskell, Representatives Kelly Skidmore and Allison Tant Request FLDOE to Release Critical Data

Florida Department of Juvenile Justice and Pinellas Technical College Host Signing Day Event for Students

  St. Petersburg, Fla. – The Florida Department of Juvenile Justice (DJJ) joined together with Pinellas … [Read More...] about Florida Department of Juvenile Justice and Pinellas Technical College Host Signing Day Event for Students

Keep in Touch

  • Email
  • Facebook
  • Twitter

Footer

News

  • Featured
  • Leaders
  • Government
  • Industry
  • Education
  • Opinion

About Us 

  • About
  • Advertise
  • Submit News
  • Contact Us

Keep in Touch

  • Email
  • Facebook
  • Twitter

Copyright © 2021
Terms & Conditions

© Copyright 2025 Capital Soup · All Rights Reserved ·